During the execution of the project, several essential activities were carried out for the proper construction of the facility. The excavation of the land began, which totaled approximately 3912.00m³, and followed by the landfill, with approximately 2974.00m³. In addition, trenches were dug along approximately 1445.00 meters for the installation of infrastructure.
To ensure the safety of the area, a 2.00 meter high mesh fence was supplied and installed over 1380 linear meters.
With regard to panels, 2,550 photovoltaic modules were installed in an area of 1,835m².
The entire execution process was carried out within

a period of 150 days.